Works completed so far:

  • 19km of fisheries walkover surveys completed on the Ottery and Kensey to identify EF sites, gravel cleaning sites, riparian habitat works and debris dams that may cause an issue.
  • 14 Fully quantitative electrofishing surveys pre and post work sites and control sites on the Inny, Ottery, Kensey and Lyd.
  • 36/60 gravel cleaning sites delivered on the Ottery and Kensey using a high pressure water pump.
  • Site visits to Roadford to develop a plan and methodology for gravel introduction and sourcing of suitable clean gravels – plan for year 1 pilot introduction.